Progress Update: Hemel-en-Aarde Road

Progress Update: Hemel-en-Aarde Road

The Overstrand Municipality welcomes the continued progress on the R53.2 million flood damage repair project along the Hemel-en-Aarde Valley Road.

The Western Cape Department of Infrastructure has been hard at work repairing major damage caused by the severe floods of September 2023, which washed away large sections of this key regional route. The scope of work includes rebuilding embankments, the road pavement structure, and drainage systems, as well as constructing four new concrete retaining walls to improve long-term stability.

To date, the project has created:

  • 1 050 person-days of employment
  • 51 local work opportunities
  • R3.2 million spent on targeted local enterprises

Project completion is expected by mid-2026. The road remains under a stop-and-go system, which will continue until the full width of the road is safe for two-way traffic.

This scenic road is not only a popular tourist route, but also a vital connector for residents, farmers, and businesses across the Overstrand and Overberg area.

The Municipality urges all road users to drive cautiously and adhere to traffic signage while repairs continue.

Previous Safer Cycling Routes on the Agenda in Overstrand towns

Mondays – Thursdays 07:45 – 13:00 & 13:30 – 16:30
Fridays 07:45 – 13:00 & 13:30 – 15:15 

Mon – Fri: 07:45 – 13:00 & 13:45 – 16:30
Cashiers: 08:00 -13:00 & 13:45 – 15:00

Website Developed and Maintained: Maxitec Internet Services Copyright © Maxitec Internet Services | All Right Reserved